Earthworks - Alderley Edge Bypass
Contract Name: Alderley Edge Bypass
Contract Value: £ 1 000 000
Form of Contract: NEC3 Option B
Client: Birse Civils
Dates: Feb - Nov 2010
Large scale earthworks and road construction including works to cuttings and structures. Carried out from February 2010 to opening by the Rt Hon George Osbourne in November 2010.
.jpg)

"Alderley Edge Bypass was opened to traffic over 6 months ahead of schedule.....The A34 Contract has been an excellent project....Many thanks for all your dedication shown throughout this contract."Birse Civils Senior Management